The Steel Frame is Complete!

The steel frame for the East Tower building is complete! On Tuesday, March 31, Skanska held the Topping Out Ceremony in which the final corner beam was raised into place. Steel decking and cement flooring are continuing to be completed throughout the building, stairways are being poured, and fireproofing will soon be completed. External walls are starting to be visible on the north portion of the building. The building will soon be a beehive of activity as both the inside and outside of the building begin to take on more definition. Construction remains on schedule – go Skanska!

bldgapril1

bldgapril

The South Half Has Begun …

The steel structure for all six floors on the north half of the building is complete. The steel construction for the first three floors on the south half of the building began this week and is moving quickly. The weather has made recent work more difficult, but progress continues nicely.

CHBS building

Steel Structure Emerging Quickly …

The steel structure for the first three floors on the north half of the building is in place, and now the top three floors on that same portion are being erected. Once all six floors on the north half of the building are in place, the steelwork for the south half of the building will begin. Kudos to Skanska, the steel workers, and all the construction personnel for their dedicated work, especially in the cold weather. The weather has caused occasional delays, but the workers have been able to make up for it by working on the weekends, keeping the project on schedule.

Steel

Steel

While We Were Away On Break …

While we were away on break, Skanska and the gang were busy at work! The steel has been erected in the northwest corner of the building for the first three floors, and the remaining wall footings have been laid for the entire building. The steel structure will continue to be erected across the north portion of the building for the first three floors while foundation work continues on the south portion of the building.

JMU - Harrisonburg-January 5th, 2015, 1042 am

 

Almost Ready for the Steel!

With the north foundation wall up and most of the west wall completed, it’s almost time for the steel to start arriving! Over the next couple of weeks the concrete foundation will be completed and the steel structure will start being erected for the north portion of the first three floors. Progress continues at a nice pace – thank you Skanska and all the workers for your dedicated work.

JMU_-_Harrisonburg-20141219-130603  173

 

Let the Building Begin!

The building has begun! The wall footings were laid on the northwest corner of the building this week, and the walls in that same area will be poured on Saturday (Nov 8). Watch the webcam as the building foundation continues to progress east and south. The foundation is scheduled to be completed around the middle of December, then the steelwork will begin!

IMG_0596

Ground Ready … Prepare to Build!

Debris removal from the old building is complete and the ground is ready for the next stage. To complete the appropriate ground preparation, substantial rock removal occurred at the northwest corner of the building site, and harder fill was brought in to achieve appropriate soil compaction levels across the building site. With that completed, storm utility work and foundation preparation work are advancing nicely. Before we know it, the building will start to materialize! Keep an eye on the webcam to see the daily progress being made.

buldingsite

Reduced to a Hole in the Ground …

With the debris almost gone, the digging has begun! Welcome to “Rock”ingham County where construction projects typically encounter some type of digging challenges due to the rock that lurks under the surface. This project has been no different, but the workers have prevailed! Very soon we will start to see construction begin. Progress continues to be on schedule.

JMU_-_Harrisonburg-20141005-155433

And Then There Was None!

The main portion of the old East Tower is now down. Only a small portion of the building remains in the southwest corner. The remaining debris is being removed (most of which is being recycled and used on other projects). Soon all that will remain will be a large hole in the ground!

Progress continues at an amazing pace, with phase two (construction) scheduled to begin in October as planned.

9-15-14

Amazing Progress!

If you want one last chance to see the old East Tower, you might want to go soon!  Demolition is progressing at an amazing pace as you can see by the photo; the building will be reduced to a pile of rubble by week’s end!

9-4-14